Concrete Works Update:
Second Floor Slab: Concrete works completed up to the second-floor slab, and wooden formwork has been removed.
Insulation: Waterproofing and insulation for foundations and retaining walls are fully completed.
Backfilling: Sand supply for backfilling the lower basement is currently at 38%.
Plastering Prep: Preparation for plastering works in both upper and lower basements reached 80%.
Water Tanks: Tank insulation preparations are currently at 60%.
Ground Floor Masonry: Brickwork/masonry for the ground floor is 75% complete.
First Floor Masonry: Brickwork/masonry for the first floor is 40% complete.